Subgranting: "Reconstruction Monitoring" Grant Program
As part of the "Spending Control for Recovery" project, the Institute for Economic Research and Policy Consulting (IER) is implementing the "Reconstruction Monitoring" grant program.
The grant program supports monitoring of the reconstruction process through two calls for proposals:
Both calls focus on monitoring the process of rebuilding and restoring social infrastructure facilities that were partially damaged or completely destroyed since February 24, 2022.
Social infrastructure includes educational institutions (preschools, schools, vocational schools, higher education institutions), healthcare facilities (primary and specialized care), cultural institutions (libraries, theatres, etc.), residential buildings, and administrative buildings.
Our Grantees:
Projects of IER grantees:
1. Monitoring of social infrastructure facilities in Chernihiv
Grantee : Public organization “Agency of Urban Initiatives”
BRP link:https://brp.org.ua/ngo/18
Region of implementation: Chernihiv community, Chernihiv region.
Deadline: March – June 2024
Project goal: To make the procedure for using budget and donor funds to restore damaged infrastructure as a result of the full-scale war in the city of Chernihiv transparent and open.
Project results:
2. Transparent reconstruction: Monitoring the reconstruction of social infrastructure facilities in the Irpin community
Grantee : Public organization “Brave Irpin”
BRP link: https://brp.org.ua/ngo/16
Implementation region: Irpin community, Kyiv region.
Deadline: March – June 2024
Project goal: Increasing transparency in the reconstruction of social infrastructure in the Irpin community, which suffered as a result of the military aggression of the Russian Federation.
Project results:
3. Restoration with transparency: public control over the reconstruction of social infrastructure in Bashtan region
Grantee : Public organization “Against Corruption”
BRP link:https://brp.org.ua/ngo/26
Region of implementation: Bashtanska community, Mykolaiv region.
Deadline: June – August 2024
Project goal: Creating systematic control of funds for Reconstruction through independent public monitoring, which involves encouraging local authorities to be transparent and accountable to the community.
Project results:
4. Monitoring the restoration of social infrastructure facilities of the Makariv territorial community
Performer:Public organization “Territorial Development Agency”
BRP link: https://brp.org.ua/ngo/23
Implementation region: Makariv community, Kyiv region.
Deadline: June – September 2024
Project goal: Establishing systematic control of Recovery funds through independent public monitoring, which involves encouraging local authorities to be transparent and accountable to the community.
Project results:
5. Monitoring of reconstruction projects in Poltava and Sumy regions financed in 2023
Grantee:Public organization “ Center for Community Development and Cooperation ”
BRP link:https://brp.org.ua/ngo/28
Implementation region: Okhtyrsk community of Sumy region, Lubensk, Dykansk, Nekhvoroshchansk communities of Poltava region.
Deadline: June – September 2024
Project objective: To increase transparency and accountability in the allocation and use of donor funds for infrastructure reconstruction projects in Ukraine by implementing monitoring tools and conducting comprehensive analysis, which will lead to a 20% reduction in the number of reports of corruption and abuse in the activities of local governments by the end of the project implementation period .
Project results:
6. Monitoring the reconstruction and restoration of educational institutions in theBuchanan, Gostomel and Borodyan communities of Kyiv region
Grantee : NGO “Women in Ukraine”
BRP link: https://brp.org.ua/ngo/25
Implementation region: Buchanan, Gostomel, and Borodyansk communities of Kyiv region.
Deadline: June – August 2024
Project goal: Strengthening public control over the quality and transparency of the reconstruction and restoration process of educational institutions in the Buchanan, Gostomel, and Borodyan communities of Kyiv region, by monitoring the reconstruction process and its results .
Project results:
7. Monitoring the restoration of social infrastructure facilities of the Makariv territorial community
Grantee : Public organization “ Territorial Development Agency ”
BRP link:https://brp.org.ua/ngo/23
Implementation region: Makariv community, Kyiv region.
Deadline: September - November 2024
Project goal: to ensure transparent monitoring of the expenditure of budget and donor funds on the restoration of social infrastructure facilities in the territory of the Makariv territorial community of the Buchansky district of the Kyiv region.
Project results:
8. Monitoring of social infrastructure facilities in Sumy, Poltava and Dnipropetrovsk regions
Grantee : Public organization “ Center for Community Development and Cooperation ”
BRP link:https://brp.org.ua/ngo/28
Region of implementation: Okhtyrsk community of Sumy region, Lubensk, Dykansk, Nekhvoroshchansk communities of Poltava region, Verkhniodniprovsk community of Dnipropetrovsk region.
Deadline: September 2024 – January 2025
Project goal: To increase the transparency of local government activities by verifying information on the implementation of reconstruction projects.
Facebook organization:
Project results:
9. Monitoring reconstruction in communities of Kyiv region in the field of education.
Grantee : NGO “ Women in Ukraine ”
BRP link:https://brp.org.ua/ngo/28
Implementation region: Buchanan, Gostomel, Borodyansk communities of Kyiv region.
Deadline: September 2024 – November 2024
Project goal: Strengthening public control over the quality and transparency of the reconstruction and restoration process of educational institutions in the Buchanan, Gostomel, and Borodyan communities of Kyiv region, by monitoring the reconstruction process and its results.
Project results:
10. Public Monitoring of Recovery: Transparency and Accountability of the Reconstruction of Social Infrastructure of Mykolaiv and Beryslav Districts
Grantee : NGO " Against Corruption "
BRP link:https://brp.org.ua/ngo/26
Implementation region: Berezanska, Nechayanska, Pervomaiska communities of Mykolaiv region, Vysokopilska, Kalynivska communities of Kherson region.
Deadline: January – March 2025
Project goal: Improve transparency and accountability of infrastructure restoration processes in affected regions through public oversight and inputting up-to-date information about reconstruction sites into the BigRecoveryPortal, which will help increase public trust and control over the efficient use of resources.
Results:
11. On-site monitoring of reconstruction and recovery: social infrastructure facilities
Grantee:Public organization "Expert and Analytical Center "Medical Designer"
BRP link:https://brp.org.ua/ngo/35
Implementation region: Nosivska, Chernihivska, Dmytrivska communities of Chernihiv region.
Deadline: January – April 2025
Project goal: Monitoring of reconstruction and restoration on site: social infrastructure facilities (reconstruction, reconstruction, restoration) that were rebuilt after significant damage or destruction in the period after February 24, 2022 .
Results :
12. Transparent reconstruction: Monitoring the reconstruction of social infrastructure facilities in the Irpin community, stage II
Grantee : NGO "Brave Irpin"
BRP link:https://brp.org.ua/ngo/16
Implementation region: Irpin community, Kyiv region.
Deadline: January – April 2025
Project goal: Increasing transparency and improving inclusiveness of the reconstruction of social infrastructure in the Irpin community, which suffered as a result of the military aggression of the Russian Federation.
Results :
13. Monitoring reconstruction in communities of Kyiv and Chernihiv regions in the field of education.
Grantee : Public organization "Women in Ukraine"
BRP link:https://brp.org.ua/ngo/25
Region of implementation: Chernihiv community of Chernihiv region, Borodyansk, Buchansk, Gostomelsk communities of Kyiv region.
Deadline: January – March 2025
Project goal: Strengthening public control over the quality and transparency of the reconstruction process (including shelters) and the restoration of educational institutions in communities of Kyiv and Chernihiv regions, by monitoring the reconstruction process and its outcome.
Results:
14. Transparent reconstruction of social infrastructure facilities in communities of Kyiv region.
Grantee : Public organization " Territorial Development Agency "
BRP link: https://brp.org.ua/ngo/23
Implementation region: Velykydymyr and Makariv communities of Kyiv region.
Deadline: January – March 2025
Project goal: to ensure transparent monitoring of the expenditure of budget and donor funds on the restoration of social infrastructure facilities in the territory of the Makariv territorial community of the Buchansky district and the Velykydymyr territorial community of the Brovary district of the Kyiv region.
Results :
15. Public Monitoring of Recovery: Transparency and Accountability of the Reconstruction of Social Infrastructure of Voznesensky and Pervomaysky Districts
Grantee:Against Corruption
BRP link: https://brp.org.ua/ngo/26
Implementation region: Voznesensky and Pervomaysky districts of Mykolaiv region - Prybuzka, Oleksandrivska, Voznesenska.
Project status: active.
Implementation period: 03.03.-03.07.2025
Goal: Improve transparency and accountability of infrastructure recovery processes in affected regions through public oversight and input of up-to-date information about recovery facilities into the BigRecoveryPortal, which will help increase public trust and control over the efficient use of resources.
Additional information
Intermediate results:
16. Monitoring of social infrastructure facilities in Chernihiv
Grantee:Public organization “Agency of Urban Initiatives”
BRP link: https://brp.org.ua/ngo/18
Implementation region: Chernihiv region - Chernihiv, Mykhailo-Kotsiubyn communities.
Project status: active.
Implementation period: 03.03.-03.07.2025
Objective: To analyze the consideration of inclusion and accessibility elements in social infrastructure facilities during reconstruction that were damaged as a result of martial law.
Additional information
Intermediate results:
17. Monitoring and reporting on the results of the reconstruction and restoration of social infrastructure in Dnipropetrovsk and Mykolaiv regions
Grantee:Public organization "Lustration Anti-Corruption Council of the Dnieper Region"
BRP link: https://brp.org.ua/ngo/50
Implementation region: Mykolaiv region - Snihurivska, Shyrokivska, Dniprovska, Smnelnikivska communities.
Project status: active.
Implementation period: 03.03.-03.07.2025
Purpose: to ensure integrity, transparency and efficiency of the use of funds from the State and local budgets and international assistance allocated for the reconstruction and restoration of social infrastructure facilities in Dnipropetrovsk and Mykolaiv regions.
Additional information
Intermediate results:
18. Monitoring the reconstruction of socially significant objects in the Lebedynska community
Grantee:Public organization “NOVA Energy”
BRP link: https://brp.org.ua/ngo/44
Implementation region: Sumy region - Lebedynska community.
Project status: active.
Implementation period: 03.03.-03.06.2025
Goal: Increasing transparency and accountability of the reconstruction processes of socially significant facilities in the Lebedyn community by implementing public monitoring mechanisms.
Additional information
Intermediate results:
19. Monitoring reconstruction in Kharkiv: ensuring transparency and efficiency of recovery
Grantee:Public organization "Agency for Local Initiatives"
BRP link: https://brp.org.ua/ngo/51
Implementation region: Kharkiv region - Kharkiv city community.
Project status: active.
Implementation period: 03.03.-03.07.2025
Goal: Through public monitoring of 10 reconstruction sites in Kharkiv, ensure accountability for spending budget funds, compliance with quality, accessibility, and energy efficiency standards, and contribute to building public trust in the city's reconstruction process.
Additional information
Intermediate results:
20. Transparent reconstruction of social infrastructure facilities on the territory of the Velykydymer territorial community
Grantee:Public organization "Territorial Development Agency"
BRP link: https://brp.org.ua/ngo/23
Implementation region: Kyiv region - Velykydymyr community.
Project status: active.
Implementation period: 03.03.-03.07.2025
Goal: to ensure transparent monitoring of the expenditure of budget and donor funds on the restoration of social infrastructure facilities in the territory of the Velykydymer territorial community of the Brovary district of the Kyiv region.
Additional information
Intermediate results:
21. Monitoring reconstruction in Bucha
Grantee:Charity organization “Sigma Irpin”
BRP link: https://brp.org.ua/ngo/41
Implementation region: Kyiv region - Buchanan community.
Project status: active.
Implementation period: 03.03.-03.07.2025
Purpose: public monitoring and publication of the results of the reconstruction of a number of objects that were selected for inspection.
Additional information
Intermediate results:
22. Monitoring the reconstruction of social infrastructure facilities in communities of Kyiv region
Grantee:Analytical Center "Socioconsulting"
BRP link: https://brp.org.ua/ngo/42
Implementation region: Kyiv region - Buchanan, Borodyansk, Irpen and Gostomel communities.
Project status: active.
Implementation period: 03.03.-03.06.2025
Goal: Ensuring public control over the quality and transparency of the reconstruction process of institutions that are to provide medical, administrative and social services to residents of the Kyiv region, including the implementation of energy efficiency technologies and compliance with accessibility standards in these facilities, by monitoring the reconstruction process and its results.
Additional information
Intermediate results:
23. Monitoring the reconstruction of the housing stock of the Kyiv region
Grantee:"COUNCIL OF THE ACCOMMODATION ASSOCIATION OF KYIV REGION"
BRP link: https://brp.org.ua/ngo/46
Implementation region: Kyiv region - Buchanan, Borodyansk and Gostomel communities.
Project status: active.
Implementation period: 03.03.-03.07.2025
Goal: to involve the local active public sector of the Kyiv region in all stages of monitoring within the framework of the Project with a focus on gaining practical experience for further public participation in future and/or already initiated restoration projects from the first stages.
Additional information
Intermediate results:
24. Our Responsibility: Monitoring Reconstruction in Poltava Oblast
Grantee:Another Woman
BRP link: https://brp.org.ua/ngo/45
Implementation region: Kremenchug, Poltava communities of Poltava region.
Project status: active.
Implementation period: 03.03.-03.07.2025
Goal: Increasing transparency and quality of restoration work through independent public monitoring of 10 sites in Poltava region.
Additional information
Intermediate results:
25. Monitoring the reconstruction and reconstruction of social infrastructure in the city of Zaporizhia and Zaporizhia region
Grantee:Center for Economic and Legal Development
Region of implementation: Zaporizhzhia community of Zaporizhzhiaoblasts
Project status: active.
Implementation period: 03.03.-03.07.2025
Objective: To carry out comprehensive monitoring of reconstructed social infrastructure facilities in Zaporizhia city and Zaporizhia region to ensure quality, transparency, and compliance with accessibility and energy efficiency standards of reconstruction. To raise public awareness of the work carried out, involve the community in discussing the reconstruction, and support public control over this process.
Additional information
Intermediate results:
26. Real reconstruction: Analyzing restored objects of Zaporizhia
Grantee:SODA
BRP link:https://brp.org.ua/ngo/48
Region of implementation: Zaporizhzhia community of Zaporizhzhiaoblasts
Project status: active.
Implementation period: 03.03.-03.06.2025
Goal: To increase the efficiency of using budget funds for reconstruction by monitoring already restored facilities, assessing their quality and compliance with the declared estimates in Zaporizhia and Zaporizhia region.
Additional information
Intermediate results:
27. Real Recovery: Safe Recovery
Grantee:Against Corruption
BRP link:https://brp.org.ua/ngo/26
Region of implementation: Dnipropetrovsk community, Dnipropetrovsk region.
Project status: active.
Implementation period: 01.06.-30.09.2025
Purpose: public control of social infrastructure in the Kryvyi Rih district.
Additional information
The project includes the following activities:
28. Monitoring of social infrastructure facilities in Chernihiv
Grantee:NGO “ Agency of Urban Initiatives ”
BRP link: https://brp.org.ua/ngo/18
Region of implementation: Chernihiv region, Chernihiv territorial community .
Project status: active.
Implementation period: 01.06.-30.09.2025
Purpose: monitoring of social infrastructure facilities in Chernihiv .
Additional information
The project includes the following activities:
29. Rebuilding Together
Grantee:Foundation "Building the Future Together"
Implementation region: Kharkiv territorial community, Kharkiv region .
Project status: active.
Implementation period: 01.06.-30.09.2025
Goal: To promote transparency, efficiency, and accountability of the process of rebuilding healthcare facilities in the city of Kharkiv by implementing systematic public monitoring in accordance with the approved IER methodology.
Additional information
The project includes the following activities:
30. Restoration for All
Grantee:Charity Foundation “COURAGEOUS”
Region of implementation: Kyiv region .
Project status: active.
Implementation period: 01.06.-30.09.2025
Goal: To increase transparency, inclusiveness, and compliance with modern standards of social infrastructure reconstruction in the Kyiv region through public monitoring of five reconstructed facilities
Additional information
The project includes the following activities:
31. Transparent reconstruction : Monitoring the reconstruction of private housing in the Irpin community , stage III
Grantee:NGO “ Brave Irpin ”
Link to the BRP portal: https://brp.org.ua/ngo/16
Implementation region: Kyiv region, Irpin community .
Project status: active.
Implementation period: 01.06.-30.09.2025
Objective: To analyze the effectiveness of the comprehensive reconstruction of the private sector in Irpin , studying the effectiveness of planning and costs , as well as taking into account modern standards of accessibility and energy efficiency when performing work .
Additional information
The project includes the following activities:
32. Hromada oversight: transparent reconstruction in the Gostomel community"
Grantee:Public ray of the future
Region of implementation: Gostomel community, Chernihiv region.
Project status: active.
Implementation period: 01.06.-30.09.2025
Goal: The project aims to enhance transparency, accountability, and efficiency of social infrastructure restoration processes in the affected Gostomel community of Kyiv region.
Additional information
The project includes the following activities:
33. Monitoring the reconstruction of educational institutions in hromadas of Kyiv and Chernihiv regions
Grantee:Public organization "Education for success"
Implementation region: Makariv and Buchan communities of Kyiv region, Ivanovo community of Chernihiv region.
Project status: active.
Implementation period: 01.06.-31.08.2025
Goal: Strengthening public control over the quality and transparency of the reconstruction process (including shelters) and the restoration of educational institutions in communities of Kyiv and Chernihiv regions, by monitoring the reconstruction process and its outcome.
Additional information
The project includes the following activities:
34. Monitoring reconstruction in Poltava region: wave 2
Grantee:NGO "Another Woman"
Link to the BRP portal:https://brp.org.ua/ngo/45
Implementation region: Kremenchuk and Myrhorod communities of Poltava region.
Project status: active.
Implementation period: 01.06.-30.09.2025
Goal: Increasing transparency and quality of restoration works through independent public monitoring of 10 social infrastructure facilities in Poltava region.
Additional information
The project includes the following activities:
35. Monitoring of reconstruction and recovery: social infrastructure facilities of Poltava region
Grantee:Analytical Center CONTENTS
Link to the BRP portal:https://brp.org.ua/ngo/29
Implementation region: Poltava region, in Poltava, Myrhorod, Lubny, Hadyatsk communities.
Project status: active.
Implementation period: 01.06.-30.09.2025
Goal: Conduct independent 4-month monitoring of 10 renovated social facilities in Poltava region (with a focus on accessibility/energy efficiency), prepare 10 video reviews and an analytical story to inform the public, contributing to the effectiveness of reconstruction costs.
Additional information
The project includes the following activities:
36. Housing reconstruction in Kyiv: monitoring of the "Window of Recovery"
Grantee:NGO “Window of Recovery”
Region of implementation: Kyiv
Project status: active.
Implementation period: 01.06.-30.09.2025
Goal: The goal of the project is to increase transparency and accountability of the reconstruction process through independent public monitoring of five damaged residential buildings in Kyiv.
Additional information
The project includes the following activities:
37. Independent public monitoring of the processes of reconstruction of social infrastructure in Kherson and Mykolaiv regions
Grantee:Charity Foundation "SKIHID-SOS" (BO "CF "SKIHID-SOS")
Implementation region: Ivanovo and Kherson communities of Kherson region, Mykolaiv and Novofedoriv communities of Mykolaiv region.
Project status: active.
Implementation period: 01.06.-31.08.2025
Goal: The goal is to implement comprehensive and objective monitoring of the reconstruction process of selected sites in accordance with the IER methodology, taking into account management decisions, quality of work, sources of funding, and community opinion, in order to increase transparency, efficiency, and social justice of reconstruction .
Additional information
The project includes the following activities:
38. Transparent reconstruction: Monitoring the reconstruction of social facilities and residential buildings in the Irpin community, stage IV
Grantee: Brave Irpin
Link to the BRP portal: https://brp.org.ua/ngo/16
Implementation region: Irpin community, Kyiv region.
Project status: active.
Implementation period: 01.06.-31.08.2025
Goal: Analyze how effective planning, implementation, and spending were
reconstruction projects in the Irpin community, as well as to investigate how much during their
implementation takes into account modern standards and requirements for barrier-free access and
energy efficiency (using the example of 15 social infrastructure and residential buildings)
houses).
Additional information
The project includes the following activities:
39. OD.nova: how Odessa overcomes the traces of tragedies
Grantee: PUBLIC ORGANIZATION "AGENCY FOR THE DEVELOPMENT OF THE LOWER DNISTER"
Region of implementation:Odessa region, Odessa .
Project status: active.
Implementation period: 01.06.-31.08.2025
Goal: strengthen public control over the quality and effectiveness of reconstruction, make it more transparent and focused on people's needs, tell the stories of destruction and reconstruction through high-quality text and video content, enter information about monitoring on the Big Recovery Portal to increase the transparency of the reconstruction process of destroyed and damaged property in the Odessa region, draw the attention of target groups to the reconstruction process taking into account all standards.
Additional information
The project includes the following activities:
40. Transparent reconstruction of Zaporizhia
Grantee:Zaporizhia Investigation Center
Region of implementation: Zaporizhia.
Project status: active.
Implementation period: 01.06.-31.08.2025
Goal: increasing the efficiency of reconstruction spending and implementation of reconstruction projects by conducting on-site monitoring of projects and surveying beneficiaries.
Additional information
The project includes the following activities:
41. Reconstruction of Zaporizhia
Grantee:People's Defense
Link to BRP: https://brp.org.ua/ngo/36
Region of implementation:Zaporizhia region, Matviyivska and Zaporizhia communities .
Project status: active.
Implementation period: 01.06.-31.08.2025
Goal: Promoting increased openness, transparency, and efficiency of reconstruction and recovery spending on the ground by monitoring the reconstruction/recovery process carried out within the framework of reconstruction and recovery projects in Zaporizhia region.
Additional information
The project includes the following activities:
1. Monitoring of reconstruction facilities in Mykolaiv region
Grantee : NON-GOVERNMENTAL ORGANIZATION “STEVE JOBS INFORMATION TECHNOLOGY SUPPORT CENTER”
BRP link:https://brp.org.ua/ngo/20
Implementation region: Bashtanska, Volodymyrivska, Mykolaivska, Nechayanska communities of Mykolaiv region.
Deadline: March – June 2024
Project goal: Increase transparency in spending on reconstruction in the Mykolaiv and Kherson regions and raise awareness among residents about spending on recovery by engaging them on the Big Recovery Portal.
Project results:
2. Monitoring of procurement for the reconstruction and restoration of social infrastructure facilities in Chernihiv region
Grantee : Public organization “Agency of Urban Initiatives”
BRP link: https://brp.org.ua/ngo/18
Region of implementation: Chernihiv community, Chernihiv region.
Deadline: June – September 2024
Project goal: Ensure transparency and accessibility to simple and understandable analysis of tender procedures for procurement of social infrastructure facilities for restoration after the full-scale invasion of the Russian Federation for both donors and residents of the region, which will allow for building trust between the population, authorities, and investors.
Project results:
3. Our control
Grantee: Public organization “Our Council”
BRP link:https://brp.org.ua/ngo/27
Implementation region: Makariv community, Kyiv region.
Deadline: July – October 2024
Project goal: Monitoring the expenditure of budget and donor funds on the reconstruction/restoration of 10 social facilities of the Makariv territorial community that were damaged after February 24, 2022, and providing information to the community, donors, and the media about the results of the monitoring, which will increase the efficiency of spending funds on reconstruction.
Project results:
4. Transparent Reconstruction: Monitoring the Procurement of Reconstruction Projects in the Irpin Community
Grantee : Public organization “Brave Irpin”
BRP link:https://brp.org.ua/ngo/16
Implementation region: Irpin community, Kyiv region.
Deadline: May - September 2024
Project goal: Increasing the transparency of procurement for the reconstruction and restoration of infrastructure in the Irpin community, which suffered as a result of the military aggression of the Russian Federation .
Project results:
5. Monitoring of reconstruction and recovery procurement in communities of Poltava region
Grantee : Public organization “ Poltava Branch of the Public Service of Ukraine ”
BRP link:https://brp.org.ua/ngo/31
Implementation region: Dykanska, Poltava, Orzhytska, Lubenska, Hradizska communities of Poltava region.
Deadline: July – October 2024
Project goal: Make the reconstruction process in communities more transparent and understandable for residents, encourage community members to participate in monitoring, increase the efficiency of spending on reconstruction, and increase the level of trust in communities.
Project results:
6. Prosovaya odgovor: Monitoring of procurement of reconstruction projects in Irpinsk community 2
Grantee : Public organization “Brave Irpin”
BRP link:https://brp.org.ua/ngo/16
Implementation region: Irpin community, Kyiv region.
Deadline: September 2024 – January 2025
Project goal: Increasing the transparency of procurement for the reconstruction and restoration of social infrastructure facilities in the Irpin community, which suffered as a result of the military aggression of the Russian Federation.
Intermediate project results:
7. Effective tools for transparent and comprehensive community recovery
Grantee : Public organization “ Poltava Branch of the Public Service of Ukraine ”
BRP link:https://brp.org.ua/ngo/31
Implementation region: Dykanska, Poltava, Orzhytska, Lubenska, Hradizska communities of Poltava region.
Deadline: November 2024 – January 2025
Project goal: Promoting citizen engagement in the recovery process in communities in the Kherson and Poltava regions through monitoring the use of reconstruction funds and conducting training events.
Intermediate project results:
8. Monitoring of reconstruction procurement in communities of Sumy and Chernihiv regions
Grantee : Public organization “Public Monitoring of Ukraine”
BRP link:https://brp.org.ua/ngo/32
Implementation region: Sumy community of Sumy region, Chernihiv community of Chernihiv region.
Deadline: September - November 2024
Project goal: Increasing the level of publicity and efficiency of the use of community funds, as well as reducing the level of corruption by monitoring procurements carried out within the framework of local reconstruction and recovery projects.
Intermediate project results:
9. Transparent reconstruction of Zaporizhzhia region
Grantee : Public organization “People's Defense”
BRP link:https://brp.org.ua/ngo/36
Implementation region: Zaporizhzhia, Molochansk, Novobohdaniv communities of Zaporizhzhia region.
Deadline: September – December 2024
Project goal: Promoting openness, transparency and efficiency of reconstruction and recovery spending on the ground by monitoring the procurement process carried out within reconstruction and recovery projects in Zaporizhia region and engaging the public in public oversight and participation in the reconstruction and recovery process.
Intermediate project results:
10. Monitoring of reconstruction and restoration procurement carried out in the territory of the Koropsk territorial community
Grantee : Public organization "Anti-Corruption Center of Korop Region "
BRP link:https://brp.org.ua/ngo/19
Implementation region: Koropska community, Chernihiv region.
Completion date: March 2024 – March 2025
Project goal: To promoteincreasing the efficiency of spending budget and donor funds allocated for the reconstruction and restoration of infrastructure facilities through monitoring of procurements carried out by the Koropsk Village Council, Novgorod-Siversky City Council, Sosnytsky Village Council, their structural divisions and municipal institutions.
Intermediate project results:
11. Control in action
Grantee : NGO "Our Council"
BRP link:https://brp.org.ua/ngo/27
Implementation region: Makarivska, Buchanska, Borodyanska communities of Kyiv region.
Deadline: January – April 2025
Project goal: monitoring the expenditure of budget and donor funds on the reconstruction/restoration of 14 social facilities of Makarivska, Buchanska, Borodyanka territorial communities of Kyiv region that were damaged after February 24, 2022, and providing information to communities, donors, and the media about the results of monitoring, which will increase the efficiency of spending funds on reconstruction.
Results:
12. Prose Reconstruction: Monitoring Procurement of Reconstruction Projects in the Irpin Community – 3
Grantee : Public organization "Brave Irpin"
BRP link: https://brp.org.ua/ngo/16
Implementation region: Irpin community, Kyiv region.
Deadline: January – April 2025
Project goal: Increasing the transparency of procurement for the reconstruction and restoration of multi-apartment residential buildings in the Irpin community, which suffered as a result of the military aggression of the Russian Federation.
Results :
13. The Right to Recovery: Protecting Property Rights and Transparency in Reconstruction
Grantee : Public Organization " Legal Development Network "
BRP link:https://brp.org.ua/ngo/39
Implementation region: Chornobaivska community, Kherson region.
Deadline: January – April 2025
Project goal: ensuring transparency and accountability of reconstruction processes in the village of Posad-Pokrovsky through public monitoring of procurement.
Result :
14. Monitoring of reconstruction and restoration procurement in the Kyiv region
Performer:Public organization "Anti-Corruption Headquarters"
BRP link: https://brp.org.ua/ngo/40
Implementation region: Kyiv, Borodyansk, Gostomelsk communities.
Deadline: January – April 2025
Project goal: To increase the transparency of spending on reconstruction in the Kyiv region and raise residents' awareness of spending issues through the use of the Big Recovery Portal tool.
Results :
15. Monitoring of reconstruction and recovery procurement on the ground in Poltava region 2.0
Grantee : NGO "Analytical Center ZMEST"
BRP link:https://brp.org.ua/ngo/29
Implementation region: Poltava, Komyshansk, Kobylyatsk, Kremenchuk communities of Poltava region.
Deadline: January – April 2025
Project goal: The project's goal is to continue monitoring procurement to increase the efficiency of reconstruction spending by identifying and preventing irregularities during procurement, ensuring transparency and accountability of the reconstruction process, involving the public in monitoring and controlling the use of budget and donor funds, and raising public awareness of the progress of reconstruction and the challenges it faces.
Results :
16. Monitoring of procurement for the reconstruction of social infrastructure
Performer : Public organization " People's Defense "
BRP link:https://brp.org.ua/ngo/36
Implementation region: Zaporizhzhia, Molochansk, Novobohdaniv communities of Zaporizhzhia region.
Deadline: January – April 2025
Project goal: Promoting openness, transparency and efficiency of reconstruction and recovery spending on the ground by monitoring the procurement process carried out within reconstruction and recovery projects in Zaporizhia region and engaging the public in public oversight and participation in the reconstruction and recovery process.
Results :
17. Transparent reconstruction of Zaporizhia and Dnipropetrovsk regions
Grantee : Public Organization " Public Monitoring "
BRP link:https://brp.org.ua/ngo/32
Implementation region: Odessa, Mykolaiv, Sumy, Kryvyi Rih, Pavlohrad communities.
Deadline: January – April 2025
Project goal: Increasing the level of publicity and efficiency of the use of community funds, as well as reducing the level of corruption by monitoring procurements carried out within the framework of local reconstruction and recovery projects.
Results :
18. Monitoring of procurement for reconstruction and rehabilitation on the ground in Poltava region
Grantee : Public organization “ SMSEST Analytical Center ”
BRP link:https://brp.org.ua/ngo/29
Implementation region: Poltava, Komyshansk, Kobylyatsk, Kremenchuk communities of Poltava region.
Deadline: July – October 2024
Project goal: The project aims to increase the efficiency of reconstruction spending by identifying and preventing irregularities during procurement, ensuring transparency and accountability of the reconstruction process, involving the public in monitoring and controlling the use of budget and donor funds, and raising public awareness of the progress of reconstruction and the challenges it faces.
Project results:
19. Monitoring of procurement for reconstruction and rehabilitation on the ground” within the framework of the project “Control of recovery costs
Grantee:Public organization "Philosophy of the Heart"
Grantee page on BRP: https://brp.org.ua/ngo/49
Implementation region: Dnipropetrovsk, Odessa regions - Pidhorodnenskaya, Kryvyi Rih, Verkhniodniprovskaya, Dniprovskaya, Avangardivskaya, Nerubayskaya communities.
Implementation period: 03.03.-03.07.2025
Objective: To increase cost efficiency and ensure transparency at all stages by monitoring procurement to accelerate recovery processes in Dnipropetrovsk and Odessa regions.
Additional information
Intermediate results:
20. Monitoring reconstruction in Kryvyi Rih
Grantee:KRYVY RIGH MEDIA
Grantee page on BRP: https://brp.org.ua/ngo/47
Implementation region: Kryvyi Rih city and Kryvyi Rih district - Kryvyi Rih, Lozuvatska, Hrushivska, Karpivska, Vakulivska communities.
Project status: active.
Implementation period: 03.03.-03.07.2025
Goal: To increase the transparency of the reconstruction processes in the city of Kryvyi Rih, Kryvyi Rih district and to raise awareness among the audience of "Pershy Kryvyi Rih (1KR.UA)" regarding expenditures from the city, district, regional, and state budgets for reconstruction.
Additional information
Intermediate results: